San Francisco / South of Market / 434 Minna St

434 Minna St

302-unit 21-story residential project to erect a type 1-a, 21-story, 302 units mixed use building (retail, residential & parking) with 2 basement levels

Complete302 UnitsAB 2011 MinisterialDBI Valuation $82.0M
Entitlement
Plan Check
Aug 2019
Awaiting Issuance
Aug 2019
Post-Issuance Addenda
Construction
Dec 2021
Complete
Dec 2021
Permit Filed
Aug 2018
Time in Active Review
12 months
Completed
Dec 2021
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

August 2019

Permit issued on August 02, 2019. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeAugust 02, 2019
Key Milestones
Aug 2018
Permit Filed
New construction permit filed with DBI
Aug 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2019
Permit Issued
Construction can begin
Dec 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Sep 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Alexander Christy.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Dec 2021
Construction startedJun 2020
Total inspections163
302 of 302 units certified for occupancy (Initial TCO, Dec 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-09-29
106FINAL INSPECT/APPRVDPASSED
2022-08-22
106FINAL INSPECT/APPRVDPASSED
2021-12-17
142PRE-FINALPASSED
2021-12-15
142PRE-FINALPASSED
2021-12-14
142PRE-FINAL
2021-12-13
142PRE-FINAL
2021-12-10
142PRE-FINAL
2021-12-09
142PRE-FINALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.