Estimated Timeline
Permit issued — plan check completeAugust 02, 2019
Key Milestones
Aug 2018
Permit Filed
New construction permit filed with DBI
Aug 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2019
Permit Issued
Construction can begin
Dec 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Sep 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Alexander Christy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Dec 2021
302 of 302 units certified for occupancy (Initial TCO, Dec 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-09-29
106FINAL INSPECT/APPRVDPASSED
2022-08-22
106FINAL INSPECT/APPRVDPASSED
2021-12-17
142PRE-FINALPASSED
2021-12-15
142PRE-FINALPASSED
2021-12-14
142PRE-FINAL
2021-12-13
142PRE-FINAL
2021-12-10
142PRE-FINAL
2021-12-09
142PRE-FINALPASSED