Estimated Timeline
Permit issued — plan check completeMarch 23, 2021
Key Milestones
Aug 2018
Permit Filed
New construction permit filed with DBI
Aug 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2018
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Mar 2021
Permit Issued
Construction can begin
Nov 2023
Construction Complete
Certificate of occupancy issued
Nov 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Nov 2023
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 14 mo · Applicant: 1 mo · Dormant: 17 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Sucre Richard.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Sucre Richard.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Jones David.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Mccormack Marcella.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Guzman Miguel.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Sep 2023
5 of 5 units certified for occupancy (CFC, Nov 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-11-09
106FINAL INSPECT/APPRVDPASSED
2023-11-06
106FINAL INSPECT/APPRVDPASSED
2023-09-25
142PRE-FINALFAILED
2023-09-19
142PRE-FINALPASSED
2023-09-18
142PRE-FINAL
2023-04-13
135SHEETROCK NAILINGPASSED
2023-04-12
135SHEETROCK NAILINGPASSED
2023-04-11
135SHEETROCK NAILINGPASSED