Estimated Timeline
0 of 6 stations approved0% complete
Key Milestones
Aug 2018
Permit Filed
New construction permit filed with DBI
Oct 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2019
Dormant Period
No plan-check activity for ~41 months — applicant-side pause, not city queue time.
Sep 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Aug 2023
Currently Dormant
No plan-check activity for 1120 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 6 mo · Applicant: 0 mo · Dormant: 89 mo
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 12, 2022. 1 round(s) of review. Reviewer: Long Ian.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Ng Joe.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Sucre Richard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Fasso Dominic.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gonzaga Janalee.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.