San Francisco / Presidio Heights / 3641 California St

3641 California St

9-unit 4-story residential project to erect 4 stories, no basement, type iii-a (l2-l4) and type i (l1), mixed use bldg with 9 residential units

Complete9 UnitsAB 2011 MinisterialDBI Valuation $3.0M
Entitlement
Plan Check
Apr 2021
Awaiting Issuance
Apr 2021
Post-Issuance Addenda
Construction
Jul 2024
Complete
Jul 2024
Permit Filed
Sep 2018
Time in Active Review
14 months
excludes 18 months dormant
Completed
Jul 2024
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

April 2021

Permit issued on April 23, 2021. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeApril 23, 2021
Key Milestones
Sep 2018
Permit Filed
New construction permit filed with DBI
Sep 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2018
Dormant Period
No plan-check activity for ~18 months — applicant-side pause, not city queue time.
Apr 2021
Permit Issued
Construction can begin
Jul 2024
Construction Complete
Certificate of occupancy issued
Jul 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jul 2024
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 1 mo · Dormant: 18 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: May Christopher.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: May Christopher.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Wong Irene.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Harshman Kjell.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Guzman Miguel.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Jun 2024
Construction startedJun 2022
Total inspections32
9 of 9 units certified for occupancy (CFC, Jul 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2024-07-25
106FINAL INSPECT/APPRVDPASSED
2024-06-07
142PRE-FINALPASSED
2024-04-18
142PRE-FINALPASSED
2023-05-11
134OK TO COVERPASSED
2023-04-24
135SHEETROCK NAILINGPASSED
2023-04-18
134OK TO COVERPASSED
2023-04-14
134OK TO COVERPASSED
2023-04-12
135SHEETROCK NAILINGPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.