San Francisco / Mission / 986 South Van Ness Av

986 South Van Ness Av

11-unit 5-story residential project erect (n) (5) story multi-family residential

Complete11 UnitsAB 2011 MinisterialDBI Valuation $2.3M
Entitlement
Plan Check
Dec 2020
Awaiting Issuance
Dec 2020
Post-Issuance Addenda
Construction
Jan 2025
Complete
Jan 2025
Permit Filed
Sep 2018
Time in Active Review
17 months
excludes 10 months dormant
Completed
Jan 2025
construction complete
Project Status
Complete
Estimated Timeline

Permit Issued

December 2020

Permit issued on December 14, 2020. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeDecember 14, 2020
Key Milestones
Sep 2018
Permit Filed
New construction permit filed with DBI
Sep 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2018
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
Dec 2020
Permit Issued
Construction can begin
Jan 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 17 mo · Applicant: 0 mo · Dormant: 10 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Flores Veronica.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Flores Veronica.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zhang Kayi.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Wong Victor.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Chung Diana.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Dec 2024
Construction startedDec 2021
Total inspections27
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-01-21
106FINAL INSPECT/APPRVDPASSED
2025-01-16
106FINAL INSPECT/APPRVDPASSED
2024-12-19
142PRE-FINAL
2024-12-18
142PRE-FINAL
2024-12-17
142PRE-FINALPASSED
2024-12-11
142PRE-FINAL
2024-08-22
135SHEETROCK NAILINGPASSED
2024-02-05
135SHEETROCK NAILINGPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.