Estimated Timeline
Permit issued — plan check completeDecember 14, 2020
Key Milestones
Sep 2018
Permit Filed
New construction permit filed with DBI
Sep 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2018
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
Dec 2020
Permit Issued
Construction can begin
Jan 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 17 mo · Applicant: 0 mo · Dormant: 10 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Flores Veronica.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Flores Veronica.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zhang Kayi.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Wong Victor.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Chung Diana.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Dec 2024
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-01-21
106FINAL INSPECT/APPRVDPASSED
2025-01-16
106FINAL INSPECT/APPRVDPASSED
2024-12-19
142PRE-FINAL
2024-12-18
142PRE-FINAL
2024-12-17
142PRE-FINALPASSED
2024-12-11
142PRE-FINAL
2024-08-22
135SHEETROCK NAILINGPASSED
2024-02-05
135SHEETROCK NAILINGPASSED