Estimated Timeline
0 of 8 stations approved0% complete
Key Milestones
Sep 2018
Permit Filed
New construction permit filed with DBI
Sep 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2018
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jun 2023
Currently Dormant
No plan-check activity for 1161 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 31 mo · Applicant: 4 mo · Dormant: 60 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Flores Veronica.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Flores Veronica.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Walls Mark.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.