Estimated Timeline
Permit issued — plan check completeApril 08, 2019
Key Milestones
Oct 2018
Permit Filed
New construction permit filed with DBI
Oct 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2019
Permit Issued
Construction can begin
Jan 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 5 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Grob Carly.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: May 2023
96 of 105 units certified for occupancy (Amended TCO, May 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-12-28
106FINAL INSPECT/APPRVDPASSED
2023-05-26
145TCO ISSUEDPASSED
2023-01-31
145TCO ISSUEDPASSED
2023-01-05
142PRE-FINAL
2023-01-04
142PRE-FINALPASSED
2023-01-03
142PRE-FINAL
2022-12-29
142PRE-FINALPASSED
2022-12-27
142PRE-FINAL