Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Alexander Christy.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Haney Tom.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Ossai Joseph.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Oct 2018
Permit Filed
New construction permit filed with DBI
Oct 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2019
Permit Issued
Construction can begin
Dec 2022
Construction Complete
Certificate of occupancy issued