Estimated Timeline
Permit issued — plan check completeJune 05, 2019
Key Milestones
Oct 2018
Permit Filed
New construction permit filed with DBI
Oct 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2019
Permit Issued
Construction can begin
Sep 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Alexander Christy.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Haney Tom.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Ossai Joseph.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Nov 2022
192 of 258 units certified for occupancy (Amended TCO, Nov 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-12-20
106FINAL INSPECT/APPRVDPASSED
2022-12-16
106FINAL INSPECT/APPRVDFAILED
2022-11-29
145TCO ISSUEDPASSED
2022-11-08
142PRE-FINAL
2022-11-03
145TCO ISSUEDPASSED
2022-10-21
145TCO ISSUEDPASSED
2022-10-17
142PRE-FINALPASSED
2022-10-12
142PRE-FINALPASSED