Estimated Timeline
Permit issued — plan check completeJuly 02, 2020
Key Milestones
Nov 2018
Permit Filed
New construction permit filed with DBI
Mar 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2019
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Jul 2020
Permit Issued
Construction can begin
Sep 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Feb 2024
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 8 mo · Applicant: 0 mo · Dormant: 8 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Dec 2022
64 of 64 units certified for occupancy (Initial TCO, Sep 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2024-02-06
142PRE-FINALPASSED
2024-02-05
106FINAL INSPECT/APPRVDPASSED
2024-02-05
142PRE-FINALPASSED
2024-01-31
142PRE-FINALFAILED
2023-06-16
111SITE VERIFICATION
2022-12-08
145TCO ISSUEDPASSED
2022-09-02
145TCO ISSUEDPASSED
2022-08-18
111SITE VERIFICATIONPASSED