Estimated Timeline
Permit issued — plan check completeApril 05, 2022
Key Milestones
Nov 2018
Permit Filed
New construction permit filed with DBI
Nov 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2019
Dormant Period
No plan-check activity for ~15 months — applicant-side pause, not city queue time.
May 2021
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Apr 2022
Permit Issued
Construction can begin
Jul 2026
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 18 mo · Applicant: 0 mo · Dormant: 22 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Durandet Kimberly.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Durandet Kimberly.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Ge Ming.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Chung Diana.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Stacy Sara.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Pre-Final Inspection
90% completeLatest inspection: Jun 2026
18 of 19 units certified for occupancy (Initial TCO, Jul 2026).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-24
800INSP QUALITY CONTROL OFFICEPASSED
2026-07-07
142PRE-FINAL
2026-07-01
142PRE-FINALFAILED
2026-06-18
142PRE-FINALPASSED
2026-04-22
142PRE-FINAL
2026-01-26
142PRE-FINAL
2024-11-01
135SHEETROCK NAILINGPASSED
2024-10-23
135SHEETROCK NAILINGPASSED