Estimated Timeline
0 of 7 stations approved0% complete
Key Milestones
Nov 2018
Permit Filed
New construction permit filed with DBI
Nov 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2019
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Feb 2020
Currently Dormant
No plan-check activity for 2381 days so far — applicant-side pause, not city queue time.
Dec 2026 – Oct 2029
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 7 mo · Applicant: 0 mo · Dormant: 86 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Alexander Christy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zhang Kayi.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.