Estimated Timeline
0 of 4 stations approved0% complete
Key Milestones
Dec 2018
Permit Filed
New construction permit filed with DBI
Dec 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2019
Dormant Period
No plan-check activity for ~14 months — applicant-side pause, not city queue time.
May 2021
Currently Dormant
No plan-check activity for 1935 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 14 mo · Applicant: 0 mo · Dormant: 78 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 4 cycle(s) to date. Reviewer: Finnegan John.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: Christensen Michael.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.