Estimated Timeline
Permit issued — plan check completeMay 14, 2019
Key Milestones
Jan 2019
Permit Filed
New construction permit filed with DBI
Jan 2019
Electronic Plan Review Activated
Plans distributed to all review stations
May 2019
Permit Issued
Construction can begin
Sep 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Apr 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 3 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Quan Sue.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jan 2023
132 of 141 units certified for occupancy (Amended TCO, Jan 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-04-24
106FINAL INSPECT/APPRVDPASSED
2023-01-24
145TCO ISSUEDPASSED
2023-01-05
145TCO ISSUEDPASSED
2022-10-18
147CEILING INSPECTION, PARTIALPASSED
2022-10-06
145TCO ISSUEDPASSED
2022-09-01
145TCO ISSUEDPASSED
2022-08-16
154OK TO COVER, PARTIALPASSED
2022-08-12
111SITE VERIFICATIONPASSED