Estimated Timeline
Permit issued — plan check completeNovember 20, 2019
Key Milestones
Feb 2019
Permit Filed
New construction permit filed with DBI
Feb 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2019
Permit Issued
Construction can begin
Nov 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Apr 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Durandet Kimberly.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chan Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 3 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 4 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Ossai Joseph.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Dec 2021
146 of 146 units certified for occupancy (Initial TCO, Nov 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-04-25
106FINAL INSPECT/APPRVDPASSED
2021-12-27
126ROUGH FRAMEPASSED
2021-10-18
124CEILING INSPECTIONPASSED
2021-09-28
124CEILING INSPECTIONPASSED
2021-09-28
124CEILING INSPECTION
2021-07-20
126ROUGH FRAMEPASSED
2021-06-23
126ROUGH FRAMEPASSED
2021-05-25
124CEILING INSPECTIONPASSED