San Francisco / Outer Mission / 4840 Mission St

4840 Mission St

137-unit 5-story residential project 100% affordable housing

Complete137 UnitsAB 2011 MinisterialDBI Valuation $70.0M
Entitlement
Plan Check
Jun 2021
Awaiting Issuance
Jun 2021
Post-Issuance Addenda
Construction
Feb 2024
Complete
Feb 2024
Permit Filed
Mar 2019
Time in Active Review
15 months
Completed
Feb 2024
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

June 2021

Permit issued on June 14, 2021. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJune 14, 2021
Key Milestones
Mar 2019
Permit Filed
New construction permit filed with DBI
Mar 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2021
Permit Issued
Construction can begin
Feb 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Oct 2024
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 15 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
In Review
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Nguyen James.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Ossai Joseph.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Feb 2024
Construction startedOct 2021
Total inspections178
137 of 137 units certified for occupancy (Initial TCO, Feb 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2024-10-16
106FINAL INSPECT/APPRVDPASSED
2024-10-09
106FINAL INSPECT/APPRVD
2024-03-07
111SITE VERIFICATIONPASSED
2024-02-16
145TCO ISSUEDPASSED
2024-02-08
111SITE VERIFICATION
2024-01-30
111SITE VERIFICATION
2024-01-24
111SITE VERIFICATION
2023-12-13
111SITE VERIFICATIONPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.