Estimated Timeline
Permit issued — plan check completeMay 23, 2023
Key Milestones
Apr 2019
Permit Filed
New construction permit filed with DBI
Apr 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2019
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Feb 2021
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
May 2023
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 31 mo · Applicant: 0 mo · Dormant: 18 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: Westoff Alex.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Westoff Alex.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Huang Vivian.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Fasso Dominic.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Garcia Jobel.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Cheng Rachel.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Nawbary Susan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.