Estimated Timeline
Permit issued — plan check completeJanuary 11, 2021
Key Milestones
May 2019
Permit Filed
New construction permit filed with DBI
May 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2019
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jan 2021
Permit Issued
Construction can begin
Dec 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Feb 2024
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo · Dormant: 11 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Feb 2024
185 of 185 units certified for occupancy (Initial TCO, Dec 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2024-02-08
142PRE-FINALPASSED
2024-02-06
106FINAL INSPECT/APPRVDPASSED
2024-01-31
142PRE-FINALFAILED
2023-11-30
111SITE VERIFICATIONPASSED
2023-11-29
111SITE VERIFICATIONPASSED
2023-11-22
146MECHANICALPASSED
2023-10-18
111SITE VERIFICATIONPASSED
2023-09-28
142PRE-FINALPASSED