San Francisco / Mission / 1629 Market St

1629 Market St

185-unit 9-story residential project mayor dir 17-02

Complete185 UnitsAB 2011 MinisterialDBI Valuation $36.0M
Entitlement
Plan Check
Jan 2021
Awaiting Issuance
Jan 2021
Post-Issuance Addenda
Construction
Dec 2023
Complete
Dec 2023
Permit Filed
May 2019
Time in Active Review
9 months
excludes 11 months dormant
Completed
Dec 2023
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

January 2021

Permit issued on January 11, 2021. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJanuary 11, 2021
Key Milestones
May 2019
Permit Filed
New construction permit filed with DBI
May 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2019
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jan 2021
Permit Issued
Construction can begin
Dec 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Feb 2024
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo · Dormant: 11 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Mcelroy Carey.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Feb 2024
Construction startedSep 2022
Total inspections49
185 of 185 units certified for occupancy (Initial TCO, Dec 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2024-02-08
142PRE-FINALPASSED
2024-02-06
106FINAL INSPECT/APPRVDPASSED
2024-01-31
142PRE-FINALFAILED
2023-11-30
111SITE VERIFICATIONPASSED
2023-11-29
111SITE VERIFICATIONPASSED
2023-11-22
146MECHANICALPASSED
2023-10-18
111SITE VERIFICATIONPASSED
2023-09-28
142PRE-FINALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.