Estimated Timeline
Permit issued — plan check completeAugust 26, 2022
Key Milestones
May 2019
Permit Filed
New construction permit filed with DBI
May 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2019
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2020
Dormant Period
No plan-check activity for ~16 months — applicant-side pause, not city queue time.
Aug 2021
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Aug 2022
Permit Issued
Construction can begin
Apr 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Feb 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 10 mo · Applicant: 0 mo · Dormant: 29 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Alexander Christy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Chan Janey.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Brownell Amy.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zhan James.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Nov 2024
5 of 5 units certified for occupancy (Initial TCO, Apr 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-02-24
106FINAL INSPECT/APPRVDPASSED
2025-02-24
106FINAL INSPECT/APPRVD
2024-11-08
142PRE-FINALPASSED
2024-11-08
142PRE-FINAL
2024-11-05
142PRE-FINALPASSED
2024-11-05
142PRE-FINAL
2024-10-31
142PRE-FINALPASSED
2024-10-31
142PRE-FINAL