Estimated Timeline
0 of 9 stations approved0% complete
Key Milestones
May 2019
Permit Filed
New construction permit filed with DBI
May 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2019
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2020
Dormant Period
No plan-check activity for ~16 months — applicant-side pause, not city queue time.
Aug 2021
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
May 2022
Dormant Period
No plan-check activity for ~23 months — applicant-side pause, not city queue time.
Apr 2024
Currently Dormant
No plan-check activity for 864 days so far — applicant-side pause, not city queue time.
Apr 2027 – Oct 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 7 mo · Applicant: 0 mo · Dormant: 80 mo
Planning (CP-ZOC)
SF Planning Department
Comments issued on April 15, 2024. 2 round(s) of review. Reviewer: Alexander Christy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Yau Willy Hoi-C.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Brownell Amy.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zhan James.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Bottleneck Watch: Fire
Fire has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.