Estimated Timeline
Permit issued — plan check completeApril 12, 2022
Key Milestones
May 2019
Permit Filed
New construction permit filed with DBI
May 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2019
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2020
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Apr 2022
Permit Issued
Construction can begin
Apr 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Feb 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo · Dormant: 18 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Alexander Christy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Chan Janey.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Nagata Timothy.
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Karalar Aytug.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Woo Jason.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Garcia Jobel.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Brownell Amy.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Oct 2024
14 of 14 units certified for occupancy (Initial TCO, Apr 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-02-20
106FINAL INSPECT/APPRVD
2025-02-20
106FINAL INSPECT/APPRVDPASSED
2024-10-29
142PRE-FINALPASSED
2024-07-29
111SITE VERIFICATIONPASSED
2024-04-26
111SITE VERIFICATIONPASSED
2024-04-26
111SITE VERIFICATION
2024-04-25
111SITE VERIFICATION
2024-04-25
111SITE VERIFICATIONPASSED