San Francisco / Outer Mission / 1830 Alemany Bl

1830 Alemany Bl

116-unit 5-story residential project erect a 5 story,2 basement, 116 dwelling residential/apartment/office bldg type 3-a

Complete116 UnitsAB 2011 MinisterialDBI Valuation $20.0M
Entitlement
Plan Check
Sep 2019
Awaiting Issuance
Sep 2019
Post-Issuance Addenda
Construction
Apr 2022
Complete
Apr 2022
Permit Filed
May 2019
Time in Active Review
4 months
Completed
Apr 2022
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

September 2019

Permit issued on September 16, 2019. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeSeptember 16, 2019
Key Milestones
May 2019
Permit Filed
New construction permit filed with DBI
May 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2019
Permit Issued
Construction can begin
Apr 2022
Construction Complete
Certificate of occupancy issued
Apr 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Apr 2022
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 4 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Flores Veronica.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Barnes Jeff.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Quan Sue.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Apr 2022
Construction startedJun 2020
Total inspections37
116 of 116 units certified for occupancy (CFC, Apr 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-04-11
106FINAL INSPECT/APPRVDPASSED
2022-04-07
142PRE-FINALPASSED
2021-12-20
135SHEETROCK NAILINGPASSED
2021-12-02
135SHEETROCK NAILINGPASSED
2021-11-18
127INSULATIONPASSED
2021-11-17
126ROUGH FRAMEPASSED
2021-11-15
127INSULATIONPASSED
2021-11-03
135SHEETROCK NAILINGPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.