Estimated Timeline
1 of 7 stations approved14% complete
Key Milestones
Jun 2019
Permit Filed
New construction permit filed with DBI
Jun 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2019
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Feb 2021
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Feb 2022
Currently Dormant
No plan-check activity for 1666 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 13 mo · Applicant: 0 mo · Dormant: 74 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Christensen Michael.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lo Buglio Nicholas.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Matsubayashi Sean.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Imson Grace.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved January 07, 2022. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.