Estimated Timeline
2 of 9 stations approved22% complete
Key Milestones
Aug 2019
Permit Filed
New construction permit filed with DBI
Aug 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2019
Dormant Period
No plan-check activity for ~23 months — applicant-side pause, not city queue time.
Aug 2021
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jun 2023
Dormant Period
No plan-check activity for ~32 months — applicant-side pause, not city queue time.
Sep 2026 – Feb 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 8 mo · Applicant: 0 mo · Dormant: 76 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on July 22, 2022. 1 round(s) of review. Reviewer: Wong Irene.
Fire (SFFD)
SF Fire Department
Comments issued on May 28, 2026. 1 round(s) of review. Reviewer: Estrella Jerry.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on June 03, 2026. 1 round(s) of review. Reviewer: Chan Calvin F.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on June 24, 2026. 1 round(s) of review. Reviewer: Imson Grace.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Comments issued on June 25, 2026. 1 round(s) of review. Reviewer: Hoang Tina.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Approved June 25, 2026. Reviewer: Hoang Tina.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Approved June 25, 2026. Reviewer: Chan Thomas.
Bottleneck Watch: Water & Sewer
Water & Sewer currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.