San Francisco / Presidio Heights / 3637 Sacramento St

3637 Sacramento St

18-unit 4-story residential project erect a 18 dwelling,4 story with 2 basements medical office, residential and retail building with parking, type 5-a

Permit Issued18 UnitsAB 2011 MinisterialDBI Valuation $5.5M
Entitlement
Plan Check
Mar 2022
Awaiting Issuance
Mar 2022
Post-Issuance Addenda
Construction
Complete
Construction: Drywall / Sheetrock (75%). Last inspection: Jul 2026.
Permit Filed
Aug 2019
Time in Active Review
22 months
excludes 9 months dormant
Permit Issued
Mar 2022
plan check complete
Project Status
Permit Issued
Estimated Timeline

Permit Issued

March 2022

Permit issued on March 11, 2022. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeMarch 11, 2022
Key Milestones
Aug 2019
Permit Filed
New construction permit filed with DBI
Aug 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2020
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Mar 2022
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 22 mo · Applicant: 0 mo · Dormant: 9 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Woods Mary.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Walls Mark.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Harshman Kjell.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
In Review
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Nawbary Susan.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Brownell Amy.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Drywall / Sheetrock
75% completeLatest inspection: Jul 2026
Construction startedJun 2025
Total inspections44
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-24
122REINFORCING STEELPASSED
2026-07-22
129SHEAR WALLPASSED
2026-07-17
135SHEETROCK NAILINGPASSED
2026-06-22
129SHEAR WALLPASSED
2026-06-18
129SHEAR WALLPASSED
2026-05-27
148OTHERPASSED
2026-05-21
135SHEETROCK NAILINGPASSED
2026-05-20
126ROUGH FRAMEPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.