San Francisco / Bayview Hunters Point / 52 Kirkwood Av

52 Kirkwood Av

77-unit 4-story residential project mayor dir# 17-02

Complete77 UnitsAB 2011 MinisterialDBI Valuation $25.4M
Entitlement
Plan Check
Jul 2020
Awaiting Issuance
Jul 2020
Post-Issuance Addenda
Construction
Sep 2023
Complete
Sep 2023
Permit Filed
Oct 2019
Time in Active Review
10 months
Completed
Sep 2023
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

July 2020

Permit issued on July 21, 2020. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJuly 21, 2020
Key Milestones
Oct 2019
Permit Filed
New construction permit filed with DBI
Oct 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2020
Permit Issued
Construction can begin
Aug 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Apr 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 10 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Hu Qi (Anne).
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Brownell Amy.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Aug 2023
Construction startedFeb 2021
Total inspections101
68 of 77 units certified for occupancy (Amended TCO, Sep 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-04-08
106FINAL INSPECT/APPRVDPASSED
2025-03-10
142PRE-FINAL
2025-03-10
142PRE-FINALFAILED
2024-11-14
111SITE VERIFICATIONPASSED
2024-11-14
111SITE VERIFICATION
2023-08-31
145TCO ISSUEDPASSED
2023-08-10
146MECHANICALPASSED
2023-06-29
146MECHANICALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.