Estimated Timeline
Permit issued — plan check completeJuly 21, 2020
Key Milestones
Oct 2019
Permit Filed
New construction permit filed with DBI
Oct 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2020
Permit Issued
Construction can begin
Aug 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Apr 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 10 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Hu Qi (Anne).
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Brownell Amy.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Aug 2023
68 of 77 units certified for occupancy (Amended TCO, Sep 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-04-08
106FINAL INSPECT/APPRVDPASSED
2025-03-10
142PRE-FINAL
2025-03-10
142PRE-FINALFAILED
2024-11-14
111SITE VERIFICATIONPASSED
2024-11-14
111SITE VERIFICATION
2023-08-31
145TCO ISSUEDPASSED
2023-08-10
146MECHANICALPASSED
2023-06-29
146MECHANICALPASSED