Estimated Timeline
0 of 4 stations approved0% complete
Key Milestones
Oct 2019
Permit Filed
New construction permit filed with DBI
Oct 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2020
Currently Dormant
No plan-check activity for 2095 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 14 mo · Applicant: 0 mo · Dormant: 69 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Guzman Miguel.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Christensen Michael.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.