San Francisco / Mission Bay / 365 Toni Stone Cg

365 Toni Stone Cg

258-unit 23-story residential project proj-19-0275

Dormant258 UnitsStandard EntitlementDBI Valuation $99.9M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 16 mo · Applicant: 0 mo
Permit Filed
Oct 2019
Time in Active Review
16 months
excludes 14 months dormant
Review Stations
0 of 4
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

No active review activity yet — estimate falls back to median durations for comparable SF projects of this size.

V0 empirical baselines from 4 unapproved stations
0 of 4 stations approved0% complete
Key Milestones
Oct 2019
Permit Filed
New construction permit filed with DBI
Oct 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2020
Dormant Period
No plan-check activity for ~14 months — applicant-side pause, not city queue time.
Mar 2022
Currently Dormant
No plan-check activity for 1627 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 16 mo · Applicant: 0 mo · Dormant: 67 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 4 cycle(s) to date. Reviewer: Zee Howard.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Theo Devine David.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Garcia Jobel.
In Review
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Christensen Michael.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.