Estimated Timeline
Permit issued — plan check completeApril 23, 2020
Key Milestones
Oct 2019
Permit Filed
New construction permit filed with DBI
Oct 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2020
Permit Issued
Construction can begin
May 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jun 2026
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 6 mo · Applicant: 1 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Cheung Jimmy.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Garcia Jobel.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: May 2025
67 of 67 units certified for occupancy (Initial TCO, May 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-06-30
106FINAL INSPECT/APPRVDPASSED
2025-05-20
145TCO ISSUEDPASSED
2025-05-13
142PRE-FINALPASSED
2025-05-12
142PRE-FINALPASSED
2025-04-21
111SITE VERIFICATIONPASSED
2025-04-09
111SITE VERIFICATIONPASSED
2025-03-14
124CEILING INSPECTIONPASSED
2025-03-14
124CEILING INSPECTION