Estimated Timeline
Permit issued — plan check completeMay 18, 2020
Key Milestones
Nov 2019
Permit Filed
New construction permit filed with DBI
Nov 2019
Electronic Plan Review Activated
Plans distributed to all review stations
May 2020
Permit Issued
Construction can begin
Jun 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Oct 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 6 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Mcelroy Carey.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Sucre Richard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jun 2022
96 of 96 units certified for occupancy (Initial TCO, Jun 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-10-05
106FINAL INSPECT/APPRVDPASSED
2022-10-03
142PRE-FINALFAILED
2022-09-29
142PRE-FINALPASSED
2022-08-18
142PRE-FINALPASSED
2022-06-22
145TCO ISSUEDPASSED
2022-06-16
111SITE VERIFICATION
2022-06-09
142PRE-FINAL
2022-06-01
124CEILING INSPECTIONPASSED