San Francisco / Hayes Valley / 78 Haight St

78 Haight St

63-unit 8-story residential project to erect 8 stories, 1 basement, type i-b, 63 residential units with child development center & office building

Complete63 UnitsAB 2011 MinisterialDBI Valuation $13.5M
Entitlement
Plan Check
Jul 2020
Awaiting Issuance
Jul 2020
Post-Issuance Addenda
Construction
Sep 2025
Complete
Sep 2025
Permit Filed
Nov 2019
Time in Active Review
8 months
Completed
Sep 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

July 2020

Permit issued on July 21, 2020. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJuly 21, 2020
Key Milestones
Nov 2019
Permit Filed
New construction permit filed with DBI
Nov 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2020
Permit Issued
Construction can begin
Sep 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 8 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Perry Andrew.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Cheung Jimmy.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Woo Jason.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Wong Kendrick.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Apr 2025
Construction startedApr 2022
Total inspections57
63 of 63 units certified for occupancy (Initial TCO, Sep 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-12-04
106FINAL INSPECT/APPRVDPASSED
2025-09-12
145TCO ISSUED
2025-09-12
142PRE-FINAL
2025-09-08
142PRE-FINAL
2025-09-02
142PRE-FINAL
2025-08-25
142PRE-FINAL
2025-05-15
133LATH, EXTERIORPASSED
2025-04-25
134OK TO COVERPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.