Estimated Timeline
0 of 5 stations approved0% complete
Key Milestones
Nov 2019
Permit Filed
New construction permit filed with DBI
Jan 2020
Electronic Plan Review Activated
Plans distributed to all review stations
May 2020
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Apr 2021
Currently Dormant
No plan-check activity for 1969 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 8 mo · Applicant: 0 mo · Dormant: 71 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 4 cycle(s) to date. Reviewer: Jones David.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Christensen Michael.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.