Estimated Timeline
0 of 10 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Hu Qi (Anne).
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Flores Veronica.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Yin Diane.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Nagata Timothy.
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chen Rong Gui Justin.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Theo Devine David.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Ossai Joseph.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2021
Permit Issued
Construction can begin
Nov 2023
Construction Complete
Certificate of occupancy issued