San Francisco / Castro/Upper Market / 250 Church St

250 Church St

24-unit 6-story residential project to erect 6 stories, no basement, type iii-a over type i-a, 24-units residential building with retail space at street level.

Approved — Awaiting Issuance24 UnitsAB 2011 Ministerial$3.5M Est. Cost
Permit Filed
Dec 2019
Active Review Since
Dec 2019
Review Stations
6 of 8
stations approved
Project Status
Approved
Estimated Timeline

Permit Issuance Estimate

November 2026 — May 2027

No active review activity yet — estimate falls back to median durations for comparable SF projects of this size.

V0 empirical baselines from 2 unapproved stations
6 of 8 stations approved75% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Hicks Bridget.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Hicks Bridget.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Approved September 05, 2023. Reviewer: Hernandez Hector.
Approved
Fire (SFFD)
SF Fire Department
Approved September 19, 2023. Reviewer: Tolentino Neil.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved October 26, 2023. Reviewer: Guzman Miguel.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved October 17, 2023. Reviewer: Arriola Laura.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 21, 2023. Reviewer: Hoffman Daniel.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved October 26, 2023. Reviewer: Blackshear John.
Approved

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.