San Francisco / Sunset/Parkside / 1360 43Rd Av

1360 43Rd Av

135-unit 5-story residential project priority project, mayor ed 13-01

Complete135 UnitsAB 2011 MinisterialDBI Valuation $40.0M
Entitlement
Plan Check
Jan 2021
Awaiting Issuance
Jan 2021
Post-Issuance Addenda
Construction
Sep 2024
Complete
Sep 2024
Permit Filed
Dec 2019
Time in Active Review
13 months
Completed
Sep 2024
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

January 2021

Permit issued on January 11, 2021. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJanuary 11, 2021
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2021
Permit Issued
Construction can begin
Sep 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Mar 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 1 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 4 cycle(s) to date. Reviewer: Mcelroy Carey.
In Review
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 1 cycle(s) to date. Reviewer: Romaidis John.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Sep 2024
Construction startedMar 2023
Total inspections286
135 of 135 units certified for occupancy (Initial TCO, Sep 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-03-05
106FINAL INSPECT/APPRVDPASSED
2024-11-26
125ROUGH FRAME, PARTIAL
2024-11-20
125ROUGH FRAME, PARTIAL
2024-10-04
142PRE-FINAL
2024-10-02
142PRE-FINAL
2024-09-30
142PRE-FINAL
2024-09-27
142PRE-FINAL
2024-09-10
145TCO ISSUED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.