Estimated Timeline
Permit issued — plan check completeJanuary 11, 2021
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2021
Permit Issued
Construction can begin
Sep 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Mar 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 1 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 4 cycle(s) to date. Reviewer: Mcelroy Carey.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 1 cycle(s) to date. Reviewer: Romaidis John.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Sep 2024
135 of 135 units certified for occupancy (Initial TCO, Sep 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-03-05
106FINAL INSPECT/APPRVDPASSED
2024-11-26
125ROUGH FRAME, PARTIAL
2024-11-20
125ROUGH FRAME, PARTIAL
2024-10-04
142PRE-FINAL
2024-10-02
142PRE-FINAL
2024-09-30
142PRE-FINAL
2024-09-27
142PRE-FINAL
2024-09-10
145TCO ISSUED