Estimated Timeline
0 of 8 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Perry Andrew.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chan Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Kevin Li.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Nawbary Susan.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Kreuscher Daniel.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2021
Permit Issued
Construction can begin
Aug 2023
Construction Complete
Certificate of occupancy issued