Estimated Timeline
0 of 7 stations approved0% complete
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2020
Dormant Period
No plan-check activity for ~16 months — applicant-side pause, not city queue time.
Aug 2022
Currently Dormant
No plan-check activity for 1476 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 16 mo · Applicant: 0 mo · Dormant: 65 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kwok Stephen.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Andrawes Kamal.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Foster Nicholas.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Kwong John.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Long Ian.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Brownell Amy.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.