Estimated Timeline
Permit issued — plan check completeJuly 08, 2022
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2020
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Oct 2021
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Jul 2022
Permit Issued
Construction can begin
Jan 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Aug 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 17 mo · Applicant: 0 mo · Dormant: 14 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Cavuslu Oguz.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Berona Marcus.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Long Ian.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Foster Nicholas.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Luu Sarah.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Brownell Amy.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jan 2025
178 of 178 units certified for occupancy (Amended TCO, Jan 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-08-29
106FINAL INSPECT/APPRVDPASSED
2025-03-06
126ROUGH FRAMEPASSED
2025-01-31
126ROUGH FRAMEPASSED
2025-01-31
126ROUGH FRAME
2025-01-30
126ROUGH FRAMEPASSED
2025-01-30
145TCO ISSUEDPASSED
2025-01-30
126ROUGH FRAME
2025-01-29
126ROUGH FRAMEPASSED