Estimated Timeline
Permit issued — plan check completeNovember 03, 2021
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2020
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Nov 2021
Permit Issued
Construction can begin
Jun 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2024
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo · Dormant: 7 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Mcelroy Carey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Andrawes Kamal.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Alexander Christy.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jun 2024
250 of 250 units certified for occupancy (Initial TCO, Jun 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2024-12-10
106FINAL INSPECT/APPRVD
2024-12-10
106FINAL INSPECT/APPRVDPASSED
2024-10-25
142PRE-FINALFAILED
2024-08-09
142PRE-FINALFAILED
2024-07-30
142PRE-FINALPASSED
2024-07-30
142PRE-FINAL
2024-07-26
142PRE-FINALPASSED
2024-07-26
142PRE-FINAL