Estimated Timeline
Permit issued — plan check completeMay 05, 2026
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2020
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
May 2021
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Dormant Period
No plan-check activity for ~20 months — applicant-side pause, not city queue time.
Mar 2026
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
May 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 26 mo · Applicant: 0 mo · Dormant: 54 mo
Planning (CP-ZOC)
SF Planning Department
Approved March 19, 2026. Reviewer: Dito Matthew.
Building Code (BLDG)
Dept. of Building Inspection
Approved April 14, 2026. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Approved April 14, 2026. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 08, 2026. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 31, 2025. Reviewer: Garcia Jobel.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved May 01, 2026. Reviewer: Nawbary Susan.
Water & Sewer QC (SFPUC-QC)
SF Public Utilities Commission
Approved November 10, 2025. Reviewer: Long Ian.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved April 15, 2025. Reviewer: Chen Bill.
Public Health (HEALTH)
Dept. of Public Health
Approved March 31, 2025. Reviewer: Lee Christina J.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved April 16, 2026. Reviewer: Blackshear John.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Approved March 26, 2025. Reviewer: Chen Bill.
Post-Issuance Addenda
Addendum #1In Review
3 of 9 stations approved· last activity 2026-08
Addendum #2In Review
5 of 14 stations approved· last activity 2026-08
Addendum #9In Review
5 of 6 stations approved· last activity 2026-07
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.