San Francisco / Hayes Valley / 444 Divisadero St

444 Divisadero St

Also known as the Touchless Car Wash site

203-unit 8-story residential project to erect 5 stories type iii-a over 3 stories type i-a mixed use 8 story building, with 203 residential dwelling units and amenity spaces, with a commercial t...

Permit Issued203 UnitsAB 2011 MinisterialDBI Valuation $47.9M
Entitlement
Dec 2024
Plan Check
May 2026
Awaiting Issuance
May 2026
Post-Issuance Addenda
Construction
Complete
Post-Issuance Addenda: 3 addenduma filed — 3 in review.
Permit Filed
Dec 2019
Time in Active Review
26 months
excludes 55 months dormant
Permit Issued
May 2026
plan check complete
Project Status
Permit Issued
Estimated Timeline

Permit Issued

May 2026

Permit issued on May 05, 2026. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeMay 05, 2026
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2020
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
May 2021
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Dormant Period
No plan-check activity for ~20 months — applicant-side pause, not city queue time.
Mar 2026
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
May 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 26 mo · Applicant: 0 mo · Dormant: 54 mo
Planning (CP-ZOC)
SF Planning Department
Approved March 19, 2026. Reviewer: Dito Matthew.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved April 14, 2026. Reviewer: Mcelroy Carey.
Approved
Fire (SFFD)
SF Fire Department
Approved April 14, 2026. Reviewer: Weiss-Ishai Sagiv.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 08, 2026. Reviewer: Dennis Rassendyll.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 31, 2025. Reviewer: Garcia Jobel.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved May 01, 2026. Reviewer: Nawbary Susan.
Approved
Water & Sewer QC (SFPUC-QC)
SF Public Utilities Commission
Approved November 10, 2025. Reviewer: Long Ian.
Approved
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved April 15, 2025. Reviewer: Chen Bill.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved March 31, 2025. Reviewer: Lee Christina J.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved April 16, 2026. Reviewer: Blackshear John.
Approved
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Approved March 26, 2025. Reviewer: Chen Bill.
Approved
Post-Issuance Addenda
Addendum #1In Review
3 of 9 stations approved· last activity 2026-08
Addendum #2In Review
5 of 14 stations approved· last activity 2026-08
Addendum #9In Review
5 of 6 stations approved· last activity 2026-07
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.