Estimated Timeline
7 of 11 stations approved63% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Cycling through 6 rounds of comments without clearing. Most recent review: April 06, 2026. Reviewer: Mcelroy Carey.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Cycling through 6 rounds of comments without clearing. Most recent review: March 25, 2026. Reviewer: Mautner Allegra.
Fire (SFFD)
SF Fire Department
Comments issued on March 21, 2026. 4 round(s) of review. Reviewer: Weiss-Ishai Sagiv.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Planning (CP-ZOC)
SF Planning Department
Approved March 19, 2026. Reviewer: Dito Matthew.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 08, 2026. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 31, 2025. Reviewer: Garcia Jobel.
Water & Sewer QC (SFPUC-QC)
SF Public Utilities Commission
Approved November 10, 2025. Reviewer: Long Ian.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved April 15, 2025. Reviewer: Chen Bill.
Public Health (HEALTH)
Dept. of Public Health
Approved March 31, 2025. Reviewer: Lee Christina J.
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved March 26, 2025. Reviewer: Chen Bill.
Bottleneck Watch: Building Code
Building Code has been the single biggest drag on this project's timeline. The reviewer has issued comments across 6 rounds of review without clearing the station. Until the underlying issues are resolved or escalated, no amount of revision cycles on other stations will unblock permit issuance.
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2026
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.