Estimated Timeline
1 of 6 stations approved16% complete
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2020
Currently Dormant
No plan-check activity for 2407 days so far — applicant-side pause, not city queue time.
Mar 2027 – Oct 2029
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 1 mo · Applicant: 0 mo · Dormant: 79 mo
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Building Code (BLDG)
Dept. of Building Inspection
Approved January 24, 2020. Reviewer: Zee Howard.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.