Estimated Timeline
2 of 7 stations approved28% complete
Plan Check Status
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Gilbraith Kathleen.
Planning (CP-ZOC)
SF Planning Department
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Mental Health (HEALTH-MH)
Dept. of Public Health
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Approved July 31, 2023. Reviewer: Chen Bill.
Building Code (BLDG)
Dept. of Building Inspection
Approved January 29, 2020. Reviewer: Zee Howard.
Bottleneck Watch: Planning
Planning has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2026 – Dec 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.