Estimated Timeline
3 of 7 stations approved42% complete
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
May 2020
Dormant Period
No plan-check activity for ~20 months — applicant-side pause, not city queue time.
Aug 2023
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Jul 2025
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 36 mo · Applicant: 0 mo · Dormant: 44 mo
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Comments issued on May 15, 2025. 1 round(s) of review. Reviewer: Chan Philip.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Building Code (BLDG)
Dept. of Building Inspection
Approved March 12, 2026. Reviewer: Soenksen Richard.
Fire (SFFD)
SF Fire Department
Approved February 12, 2026. Reviewer: Estrella Jerry.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved April 09, 2025. Reviewer: Fong Jeffrey.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.