Estimated Timeline
Permit issued — plan check completeMay 24, 2021
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2020
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2021
Permit Issued
Construction can begin
May 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Oct 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 5 mo · Applicant: 0 mo · Dormant: 7 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Hicks Bridget.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Liu Stephen.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: May 2023
195 of 203 units certified for occupancy (Amended TCO, May 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-10-17
106FINAL INSPECT/APPRVDPASSED
2023-05-15
145TCO ISSUEDPASSED
2023-04-14
142PRE-FINALPASSED
2023-04-11
111SITE VERIFICATIONFAILED
2023-04-11
111SITE VERIFICATIONPASSED
2023-02-15
126ROUGH FRAMEPASSED
2023-02-15
111SITE VERIFICATIONPASSED
2023-02-10
126ROUGH FRAMEPASSED