San Francisco / Presidio Heights / 401 Cherry St

401 Cherry St

34-unit 7-story residential project building b12

Dormant34 UnitsAB 2011 MinisterialDBI Valuation $57.5M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 1 mo · Applicant: 0 mo
Permit Filed
Dec 2019
Time in Active Review
1 month
excludes 43 months dormant
Review Stations
0 of 6
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

April 2027 — October 2028

No active review activity yet — estimate falls back to median durations for comparable SF projects of this size.

V0 empirical baselines from 6 unapproved stations
0 of 6 stations approved0% complete
Key Milestones
Dec 2019
Permit Filed
New construction permit filed with DBI
Dec 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2020
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Jun 2021
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Currently Dormant
No plan-check activity for 1119 days so far — applicant-side pause, not city queue time.
Apr 2027 – Oct 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 1 mo · Applicant: 0 mo · Dormant: 79 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: May Christopher.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Not Yet Routed
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Not Yet Routed
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Not Yet Routed
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Not Yet Routed

Bottleneck Watch: Fire

Fire has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.