Estimated Timeline
11 of 11 stations approved100% complete
Key Milestones
Jan 2020
Permit Filed
New construction permit filed with DBI
Feb 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
May 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
May 2025
Currently Dormant
No plan-check activity for 457 days so far — applicant-side pause, not city queue time.
Sep 2026 – Sep 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 32 mo · Applicant: 10 mo · Dormant: 24 mo
Planning (CP-ZOC)
SF Planning Department
Approved May 08, 2025. Reviewer: Botn Kurt.
Mechanical (MECH)
Dept. of Building Inspection
Approved May 15, 2025. Reviewer: Tan (Peter) Jia Jian.
Building Code (BLDG)
Dept. of Building Inspection
Approved October 29, 2024. Reviewer: Hernandez Hector.
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Approved April 22, 2025. Reviewer: Cheng Jason.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved May 02, 2025. Reviewer: Fong Jeffrey.
Fire (SFFD)
SF Fire Department
Approved November 01, 2024. Reviewer: Ziegler Erik.
Public Health (HEALTH)
Dept. of Public Health
Approved November 19, 2024. Reviewer: Hoang Tina.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved October 30, 2023. Reviewer: Choy Clinton.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved January 04, 2024. Reviewer: Nawbary Susan.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved February 24, 2025. Reviewer: Tjalsma Jason.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved May 27, 2025. Reviewer: Blackshear John.