San Francisco / Twin Peaks / 407 Burnett Av

407 Burnett Av

9-unit 9-story residential project erect a 9 story, 9 dwelling condos, no basement type i-a.

In Plan Check9 UnitsAB 2011 MinisterialDBI Valuation $4.0M
Entitlement
Opened Mar 2023
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 26 months in active review. City desk: 26 mo · Applicant: 0 mo
Permit Filed
Feb 2020
Time in Active Review
26 months
excludes 53 months dormant
Review Stations
0 of 9
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

Timeline driven by 3 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 9 unapproved stations
0 of 9 stations approved0% complete
Key Milestones
Feb 2020
Permit Filed
New construction permit filed with DBI
Feb 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2020
Dormant Period
No plan-check activity for ~18 months — applicant-side pause, not city queue time.
Feb 2022
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Mar 2024
Dormant Period
No plan-check activity for ~27 months — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 26 mo · Applicant: 0 mo · Dormant: 53 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on March 15, 2024. 2 round(s) of review. Reviewer: Barnes Jeff.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on August 07, 2023. 1 round(s) of review. Reviewer: Estrella Jerry.
Comments Issued
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Comments issued on January 29, 2024. 2 round(s) of review. Reviewer: Yin Diane.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Jimenez Sylvia.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Campbell Cathleen.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Fong Jeffrey.
In Review
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Hoffman Daniel.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.