Estimated Timeline
7 of 7 stations approved100% complete
Key Milestones
Feb 2020
Permit Filed
New construction permit filed with DBI
Feb 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2020
Dormant Period
No plan-check activity for ~27 months — applicant-side pause, not city queue time.
Oct 2022
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Jul 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2024
Currently Dormant
No plan-check activity for 787 days so far — applicant-side pause, not city queue time.
Sep 2026 – Sep 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 16 mo · Applicant: 0 mo · Dormant: 62 mo
Planning (CP-ZOC)
SF Planning Department
Approved July 18, 2023. Reviewer: Gordon-Jonckheer Elizabeth.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 01, 2024. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved April 12, 2024. Reviewer: Arriola Laura.
Building Code (BLDG)
Dept. of Building Inspection
Approved April 09, 2024. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Approved August 09, 2023. Reviewer: Estrella Jerry.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved April 15, 2024. Reviewer: Huang Vivian.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved August 09, 2023. Reviewer: Blackshear John.