Estimated Timeline
7 of 7 stations approved100% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Approved July 18, 2023. Reviewer: Gordon-Jonckheer Elizabeth.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 01, 2024. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved April 12, 2024. Reviewer: Arriola Laura.
Building Code (BLDG)
Dept. of Building Inspection
Approved April 09, 2024. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Approved August 09, 2023. Reviewer: Estrella Jerry.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved April 15, 2024. Reviewer: Huang Vivian.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved August 09, 2023. Reviewer: Blackshear John.
Key Milestones
Feb 2020
Permit Filed
New construction permit filed with DBI
Feb 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Apr 2026 – May 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.