Estimated Timeline
Permit issued — plan check completeSeptember 29, 2021
Key Milestones
Jun 2020
Permit Filed
New construction permit filed with DBI
Jun 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2021
Permit Issued
Construction can begin
Jun 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Kwok Stephen.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Durandet Kimberly.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 3 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Chung Diana.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Andrawes Kamal.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jun 2025
157 of 157 units certified for occupancy (Initial TCO, Jun 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-12-04
106FINAL INSPECT/APPRVDPASSED
2025-08-07
142PRE-FINAL
2025-08-05
142PRE-FINAL
2025-07-11
142PRE-FINAL
2025-06-25
145TCO ISSUEDPASSED
2025-06-23
142PRE-FINALPASSED
2025-06-16
134OK TO COVER
2025-06-13
134OK TO COVER