San Francisco / Potrero Hill / 1801 25Th St

1801 25Th St

157-unit 7-story residential project priority processing - 100 % affordable housing

Complete157 UnitsAB 2011 MinisterialDBI Valuation $80.0M
Entitlement
Plan Check
Sep 2021
Awaiting Issuance
Sep 2021
Post-Issuance Addenda
Construction
Jun 2025
Complete
Jun 2025
Permit Filed
Jun 2020
Time in Active Review
16 months
Completed
Jun 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

September 2021

Permit issued on September 29, 2021. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeSeptember 29, 2021
Key Milestones
Jun 2020
Permit Filed
New construction permit filed with DBI
Jun 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2021
Permit Issued
Construction can begin
Jun 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Kwok Stephen.
In Review
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Durandet Kimberly.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 3 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Chung Diana.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Jun 2025
Construction startedSep 2022
Total inspections223
157 of 157 units certified for occupancy (Initial TCO, Jun 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-12-04
106FINAL INSPECT/APPRVDPASSED
2025-08-07
142PRE-FINAL
2025-08-05
142PRE-FINAL
2025-07-11
142PRE-FINAL
2025-06-25
145TCO ISSUEDPASSED
2025-06-23
142PRE-FINALPASSED
2025-06-16
134OK TO COVER
2025-06-13
134OK TO COVER
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.