Estimated Timeline
7 of 7 stations approved100% complete
Key Milestones
Aug 2020
Permit Filed
New construction permit filed with DBI
Aug 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2021
Dormant Period
No plan-check activity for ~18 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jun 2023
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Jan 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2024
Currently Dormant
No plan-check activity for 783 days so far — applicant-side pause, not city queue time.
Sep 2026 – Sep 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 10 mo · Applicant: 0 mo · Dormant: 62 mo
Planning (CP-ZOC)
SF Planning Department
Approved January 27, 2024. Reviewer: Horn Jeffrey.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved February 20, 2024. Reviewer: Dottson Marcus.
Building Code (BLDG)
Dept. of Building Inspection
Approved June 28, 2024. Reviewer: Barnes Jeff.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved April 17, 2024. Reviewer: Choy Clinton.
Fire (SFFD)
SF Fire Department
Approved April 15, 2024. Reviewer: Carreira Bela.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved February 08, 2024. Reviewer: Arriola Laura.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 27, 2024. Reviewer: Blackshear John.