San Francisco / Excelsior / 5425 Mission St

5425 Mission St

50-unit 6-story residential project to erect a 6-story, type 5 over type 1a, 50 residential unit, mixed ues bldg with commercial, parking garage and one basement.**comply to maher ord# 155-13,...

Dormant50 UnitsAB 2011 MinisterialDBI Valuation $5.5M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 5 mo · Applicant: 0 mo
Permit Filed
Sep 2020
Time in Active Review
5 months
excludes 60 months dormant
Review Stations
4 of 9
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
4 of 9 stations approved44% complete
Key Milestones
Sep 2020
Permit Filed
New construction permit filed with DBI
Sep 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2020
Dormant Period
No plan-check activity for ~20 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Dormant Period
No plan-check activity for ~18 months — applicant-side pause, not city queue time.
Jan 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Apr 2025
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Jan 2026
Currently Dormant
No plan-check activity for 212 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 5 mo · Applicant: 0 mo · Dormant: 66 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on April 01, 2025. 1 round(s) of review. Reviewer: Ospital Joseph.
Comments Issued
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Comments issued on April 03, 2025. 1 round(s) of review. Reviewer: Hoang Tina.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on April 24, 2025. 1 round(s) of review. Reviewer: Estrella Jerry.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on April 25, 2025. 4 round(s) of review. Reviewer: Wong Laura.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Planning (CP-ZOC)
SF Planning Department
Approved January 24, 2025. Reviewer: Horn Jeffrey.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved March 24, 2025. Reviewer: Dennis Rassendyll.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved March 20, 2025. Reviewer: Lee Christina J.
Approved
Water & Sewer QC (SFPUC-QC)
SF Public Utilities Commission
Approved January 27, 2026. Reviewer: Hoe Cynthia.
Approved

Bottleneck Watch: Building Code

Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.