Estimated Timeline
4 of 9 stations approved44% complete
Key Milestones
Sep 2020
Permit Filed
New construction permit filed with DBI
Sep 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2020
Dormant Period
No plan-check activity for ~20 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Dormant Period
No plan-check activity for ~18 months — applicant-side pause, not city queue time.
Jan 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Apr 2025
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Jan 2026
Currently Dormant
No plan-check activity for 212 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 5 mo · Applicant: 0 mo · Dormant: 66 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on April 01, 2025. 1 round(s) of review. Reviewer: Ospital Joseph.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Comments issued on April 03, 2025. 1 round(s) of review. Reviewer: Hoang Tina.
Fire (SFFD)
SF Fire Department
Comments issued on April 24, 2025. 1 round(s) of review. Reviewer: Estrella Jerry.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on April 25, 2025. 4 round(s) of review. Reviewer: Wong Laura.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Planning (CP-ZOC)
SF Planning Department
Approved January 24, 2025. Reviewer: Horn Jeffrey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved March 24, 2025. Reviewer: Dennis Rassendyll.
Public Health (HEALTH)
Dept. of Public Health
Approved March 20, 2025. Reviewer: Lee Christina J.
Water & Sewer QC (SFPUC-QC)
SF Public Utilities Commission
Approved January 27, 2026. Reviewer: Hoe Cynthia.
Bottleneck Watch: Building Code
Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.